Facilities Update - December 21, 2021
On Monday, December 27, 2021 and Tuesday, December 28, 2021, the lights and/or outlets in the following areas will be off:
B-Building first floor (lights and outlets)
B-Building third floor administration area (lights)
D-Building third floor classrooms (lights)
The electric panels will be replaced and power to the lights and duplex outlets will be restored no later than Tuesday evening.
If you have questions or comments, please contact the Facilities department.
Source: All-College Email
Facilities Update - December 16, 2021
Bunker Hill Community College (BHCC) in conjunction with the Department of Capital Asset Management and Maintenance (DCAMM), Thompson Engineering, NBBJ Architects, and Bond Building, will replace the electrical infrastructure this spring. There will be considerable activity on the grounds and roadways as trench excavation and underground duct banks are installed to serve new transformers and switchgear. We will keep you posted regarding construction start dates, estimated duration of tasks, and road closures.
A more immediate project is taking shape internally. In addition to the electrical infrastructure, BHCC has received funding to replace the internal electrical subpanels that feed boilers, pumps, motors, lighting, and duplex outlets. The panels are located throughout the College in the electric closets on each floor and the tunnel. On December 16, work is taking place on the D1 lighting panel. Scheduled for December 17 is lighting panel D2. We are consulting the classroom schedule to identify work areas to minimize the impact on faculty, staff, or students.
The electrical contractor is scheduled to work during the BHCC winter maintenance shut down. As a result, multiple lighting and convenience panels will be replaced between December 24, 2021, and January 3, 2022. Work is scheduled through the winter break until the spring semester. We will consult the classroom schedule for Intercession room assignments to minimize possible disruption to students, faculty, and staff.
The construction of the new building will begin in the spring of ’2022!
Please contact BHCC Facilities with questions or comments.
Source: All-College Email
Facilities Update - November 12, 2021
As we near the end of the elevator replacement project, we are required to have the elevators tested for compliance to the code and proper safe operation. The service elevator to the kitchen (E3) and the B-Building (B1) elevator are scheduled to be tested on November 17, 2021.
Please note:
The fire alarm system associated with the elevators will be tested. If there is an emergency, you will receive directions from Public Safety.
Source: All-College Email
Facilities Update - November 8, 2021
Bunker Hill Community College has contracted to replace the energy recovery wheel located on the roof of the G-building. To accomplish the replacement there will be a crane parked on the perimeter road opposite the side entrance to the G-building athletics department. The road will remain open during this time. Please be cautious.
Facilities Update - August 25, 2021
Please find below an updated report on the elevator replacement project:
- Elevator Car E1 (near E175) has been replaced and inspected
- Elevator Car D1 has been replaced and inspected
- Elevator Car E3 service elevator to the kitchen is under construction
- Elevator Car B1 is under construction
- Elevator Car E2 (near women’s restroom) will be taken out of service in two weeks
All elevator construction is expected to be complete in late November 2021.
We appreciate your patience as we continue to upgrade the physical plant.
Source: All-College Email
Facilities Update - August 12, 2021
The B-Building elevator will be taken offline on Monday, August 16, 2021, to be replaced. The scheduled outage is through October. The D-Building elevator has been replaced and is running properly. Please plan your route accordingly.
Thank you for your continued patience, understanding, and support as we continue building improvements.
Source: All-College Email
Facilities Update - August 9, 2021
From Tuesday, August 10 through Friday, August 13, 2021, fire alarm testing is scheduled for all buildings on the Charlestown Campus. The testing will be completed by end of day Friday, August 13. During testing, you may hear intermittent alarms, horns, and see flashing strobes. Please remember this is only a test. In an actual emergency, you will receive instructions from Campus Police and/or the Boston Fire Department.
Source: All-College Email
Facilities Update - July 26, 2021
BHCC is replacing six valves in the fire pump Tuesday, July 27, 2021, and Wednesday, July 28, 2021. Work will continue the following week, August 2-4, replacing the fire pump and automatic controller. In conjunction with Boston Fire Department, the State Building Inspector has requested a fire watch be in place during the time of this installation as the system will not be functional. You may see fire personnel and fire equipment at BHCC. This is not an emergency, simply a best practice precaution.
Thank you for your patience and understanding as BHCC continues to update equipment.
Sent on behalf of John Chirichiello, Director of Facilities Management
As we move towards returning to campus, all facility work orders shall be placed through Workplace Essentials. Workplace Essentials can be accessed by logging in to the BHCC Intranet then going to Facilities. There, you will see a link to “submit a work order.” Click on the link and fill in the request. Thank you!
Source: All-College Email
Facilities Update - July 16, 2021
The time is finally upon us! Construction activity will begin on the Charlestown campus on Monday July 19, 2021. It will only last 2-3 weeks, as this is drilling of test wells, digging test pits, and establishing water recharge rates.
We are excited that this project is moving forward. Please watch out for the heavy equipment and observe fencing and warnings. Stay safe!
Source: All-College Email
Facilities Update - June 17, 2021
The express service elevator to the Aladdin kitchen is scheduled to be closed for replacement on Monday, June 21, 2021. The elevator will be out of service for approximately 8 weeks during the replacement process.
Please contact Facilities with questions or comments.
Source: All-College Email
Facilities Update - May 13, 2021
On Monday, May 17, Tuesday, May 18, and Wednesday, May 19, fire alarm testing is scheduled for all buildings on the Charlestown Campus. The testing will be completed on May 19, 2021, by the end of the day. During testing, you may hear intermittent alarms, horns and see flashing strobes. Please remember this is only a test. In an actual emergency during this time, you will receive instructions from Campus Police and/or the Boston Fire Department.
Source: All-College Email
Facilities Update - March 10, 2021
BHCC will begin the Elevator Replacement project on Monday March 15, 2021. The scheduled completion date for the replacement of E-Building Car 1 and D-Building Car 1 is June 4, 2021.
Elevator replacement of E-Building Car 2, B-Building Car 1 and E-Building Car 3 (express to the kitchen) will be begin Monday June 7, 2021 and will be completed on Friday September 10, 2021.
BHCC discussed the importance of safety and housekeeping this morning at the project kickoff meeting. We will inspect the work areas throughout the day to ensure the safety of the BHCC students, faculty, staff and construction personnel.
We encourage you to be vigilant as you walk past the elevators during the project. There are, as you can imagine, a myriad of parts and pieces that must be removed prior to the installation of the new equipment.
Please contact Facilities at 617-228-2240 with questions or comments.
Source: All-College Email
Facilities Update - March 8, 2021
Fire alarm testing is scheduled for Monday, March 15, Tuesday, March 16, and Wednesday, March 17, for all Charlestown Campus buildings. The testing will be completed end of the day on March 17, 2021. During testing, you may hear intermittent alarms, horns and see flashing strobes. Please remember this is only a test. In an actual emergency during this time, you will receive instructions from Campus Police and/or the Boston Fire Department.
Source: All-College Email
Facilities Update - February 22, 2021
On March 1, 2021, there will be limited access to the Perimeter Road starting at 6 a.m. due to a crane and flatbed truck setting a piece of equipment on the D-Building roof. The road will remain open; however, if you are coming to campus, we ask that you enter and exit via the road between Parking Lots 1 & 2. To access the main campus from Rutherford Avenue, please cross Austin Street and turn right and enter BHCC between Parking Lots 1 & 2.
Thank you for your continued cooperation.
Source: All-College Email
Facilities Update - December 2, 2020
Fire alarm testing is scheduled for Thursday, December 10, and Friday, December 11, for all buildings on the Charlestown Campus. The testing will be completed on December 11, 2020, by the end of the day.
During testing, you may hear intermittent alarms, horns, and see flashing strobes. Please remember this is only a test. In the event of an actual emergency, you will receive instructions from Campus Police and/or the Boston Fire Department.
Source: All-College Email
Facilities Update - November 11
Good afternoon.
BHCC Facilities department has confirmed 2 fire hydrants will be flow tested on Monday November 16, 2020. The information from the flow test will be used to determine the design for the fire suppression and plumbing systems in the new BHCC “N” building.
Please note the water inside BHCC may appear to be cloudy or rusty in color immediately after the flow test. BHCC facilities staff will operate all plumbing fixtures until the water runs clear.
The flow test will discharge a large volume of water onto the roadway. The water will eventually make its way to the storm water system.
If walking or driving near the hydrants located near parking lot 4 or G building during the flow test, please exercise caution.
If you have questions or comments please contact BHCC Facilities at 2240.
Source: All-College Email
Facilities Update - October 8
On Friday, October 9 at 9 a.m. we will be checking our Leak Detection System for the chillers. The testing will be completed in approximately 2 hours. During testing, you may hear intermittent alarms, horns and see flashing strobes in the basement area. Please remember this is only a test. In the event of an actual emergency, you will receive instructions from Campus Police and/or the Boston Fire Department.
Facilities Update - August 20, 2020
The perimeter road at the Charlestown Campus will be closed on Friday, August 21 from 6:30-7:30 a.m. to allow for power washing. During the road closure, traffic on the perimeter road will be required to exit to Rutherford Ave. To access the main campus from Rutherford Ave., please cross Austin St. and turn right and enter BHCC between Parking Lots 1 & 2.
Source: All-College Email
Construction Update – July 7, 2020
The general contractor will be setting the concrete pump in Parking Lot 4 on Thursday July 9, 2020 to pour concrete on the B-Building roof (weather permitting). Please arrange to park in another parking lot if you are coming to BHCC on Thursday.
Construction Update – July 6, 2020
The perimeter road at the Charlestown Campus will be closed on Friday, July 10, 2020. The road closure work is weather dependent. During the road closure, traffic on the perimeter road will be required to exit to Rutherford Ave. To access main campus from Rutherford Ave., please cross Austin St. and turn right and enter BHCC between Parking Lots 1 & 2.
Source: All-College Email
Construction Update – June 18, 2020
The general contractor will be setting the concrete pump in parking lot 4 on Friday June 19, 2020 to pour concrete on the B-Building roof. Please arrange to park in another parking lot if you are coming to BHCC on Friday.
Construction Update - June 12, 2020
The perimeter road at the Charlestown Campus may be closed on Tuesday, June 16, 2020 and Thursday, June 18, 2020 to set up a concrete pump truck as part of the B-Building roof repairs. This work is weather dependent. During the road closure, traffic on the perimeter road will be required to exit to Rutherford Ave. To access main campus from Rutherford Ave., please cross Austin St. and turn right and enter BHCC between Parking Lots 1 & 2.
Source: All-College Email
Facilities Update - May 5, 2020
Sent on behalf of Gary Bigelow, Executive Director Facilities Planning, Construction & Energy Management
Good afternoon.
With warmer weather rapidly approaching, I wish you all the best! Time to get out and loosen up a bit after the long winter and extraordinarily challenging spring. I hope you are well and thinking of what the “new” normal means to you.
BHCC is beginning the Building B roof and skylight replacement project. This project is being funded by the Division of Capital Asset Management and Maintenance, (DCAMM), through our Deferred Maintenance Fund.
This project is kicking off on Friday May 8, 2020 with the delivery of 11 trailer loads of roofing materials, with work slated to begin on Monday May 11, 2020. The project duration is 220 days; however, with the campus offering remote summer classes and limited staff on campus, we will gain some efficiency, allowing a more timely completion.
There will be dumpsters in the parking spaces along perimeter road from time to time to collect the roofing materials being removed. The contractors will periodically request we close the perimeter road to allow crane access as required to remove material from the roof and stock new material on the roof. I have requested a few days notification prior to any road closures so that timely notification can made to the BHCC community.
Replacing the roof and skylights is a substantial undertaking. The contractors will comply with DCAMM guidelines for construction during COVID-19. , They will be required to wear face coverings and gloves and practice social distancing where practical.
BHCC has designated one stair way for the contractors use and designated the 3rd floor B – building women’s rest room for their use with appropriate signage indicating this use. The contractors will be using the stairs to the right of Security on B1 and will be required to sign in and out with Security. Other areas of the school will be off limits and caution tape will be installed to identify those “off limits” areas.
Periodic updates will be provided as the project progresses.
Please direct any questions or comments to: gbigelow@bhcc.edu or call 617-936-1985.
Be safe!
Gary
Source: All-College Email
Facilities Update - February 17, 2020
Source: All-College Email
Construction Updates - February 11, 2020
The stairway leading from Parking Lot 3 to the pedestrian Plaza will be closed Sunday, February 16, 2020. If the stairway is closed during your visit to campus, please follow the directions for access below:
Notes for Access to Charlestown Campus During the Stairway Closure
- Anyone parking or being dropped off in Parking Lots 1, 2 or 3, should enter the building on the ground floor of B-Building (entrance adjacent to Parking Lot 4).
- If the College is closed, visitors will need to walk down the street and enter the campus through the entrance to Parking Lots 1 &2.
Facilities Update - January 23, 2020
The stairway leading from Parking Lot 3 to the pedestrian Plaza will be closed periodically from Saturday, January 25, 2020, to Sunday, January 26, 2020, to complete the installation of a stairway handrail. If the stairway is closed during your visit to campus, please follow the directions for access below:
Notes for Access to Charlestown Campus During the Stairway Closure
- Anyone parking or being dropped off in Parking Lots 1, 2 or 3, should enter the building on the ground floor of B-Building (entrance adjacent to Parking Lot 4).
- If the College is closed, visitors will need to walk down the street and enter the campus through the entrance to Parking Lots 1 &2.
Source: All-College Email
Facilities Update - January 6, 2020
Fire alarm testing is scheduled for today for all buildings on the Charlestown Campus. The testing will be completed by the end of the day on January 7, 2020.
During testing, you may hear intermittent alarms, horns and see flashing strobes. Please remember this is only a test. In the event of an actual emergency during this time you will receive instructions from Campus Police and/or Boston Fire Department.
Source: All-College Email
Facilities Update - January 6, 2020
Dear Faculty and Staff,
As many of you know, we are in the process of updating the locks throughout the Charlestown Main Campus. If you are in a staff or faculty office in the B or D-Building, please stop by E120 to return your existing key and pick up your new key.
Sorry for the inconvenience.
Source: All-College Email
Construction Updates - November 22, 2019
Dear BHCC Faculty and Staff,
We once again need to make weekend emergency repairs to the heating system. This weekend, emergency repairs will be made to the central heating plant on the Charlestown Campus. All buildings on the Charlestown Campus will be affected.
Beginning Saturday, November 23, the heating system will be turned off in order for a new condensate tank to be installed over the weekend. The heat will be functioning again on Monday, November 25.
If you will be on campus this weekend, please dress warmly while the work is performed.
Source: All-College Email
Facilities Update - October 30
Dear BHCC Faculty and Staff,
This weekend, emergency repairs will be made to the central heating plant on the Charlestown Campus. All buildings on the Charlestown Campus will be affected.
Beginning Friday afternoon, November 1, the heating system will be turned off in order for a new condensate tank to be installed over the weekend. The heat will be functioning again on Monday, November 4.
If you will be on campus this weekend, please dress warmly while the work is performed.
Source: All-College Email
Construction Updates - September 24, 2019
On September 27, 2019, BHCC will begin removing and replacing the stairs that connect the Plaza and Parking Lot 3 (located under the Gilmore Bridge). The project is expected to take 30 days, weather permitting. During construction, please be extra cautious as you travel through the area.
Notes for Access to Charlestown Campus
- Anyone parking or being dropped off in Parking Lots 1, 2 or 3, should enter the building on the ground floor of B-Building (entrance adjacent to Parking Lot 4). If the College is closed, visitors will need to walk down the street and enter the campus through the entrance to Parking Lots 1 &2.
- The parking spaces closest to the Plaza stairs of Lot 3 may be temporarily closed to allow for the removal of debris and the pouring of concrete.
- There will be no access from Parking Lot 3 to the Plaza during demolition and construction of the stairway.
Source: All-College Email
Facilities Update - September 20, 2019
The E-building elevator (Car 1), adjacent to the G-Building will have a staff member operating this elevator during Library and Learning Commons hours of operation to provide access to the 3rd floor.
When leaving the library and elevator access is needed, please see the Library’s front desk and they will provide access. This should be resolved by Tuesday, September 24.
The library hours of operation are:
Monday - Thursday: 8 a.m. - 9 p.m.
Friday: 8 a.m. - 8 p.m.
Saturday: 8 a.m. - 4 p.m.
Sunday: 10 a.m. - 4 p.m.
The Library and Learning Commons is located on the 3rd floor of the E-building and is also available by stairs.
We apologize for the inconvenience.
Source: All-College Email
Facilities Update - September 20, 2019
The E-Building elevator (Car 2), located adjacent to the D-Building, is out of order. This elevator is expected to be closed until the end of next week, pending the arrival of a special-order part necessary for repair. The other E-building elevator (Car 1), adjacent to the G-Building, is operational. Currently, the only way to access the BHCC Library and Learning Commons is by stair. On Tuesday, September 24, alterations to the E-Building elevator Car 1 will be made so that it can also access the BHCC Library.
We apologize for the inconvenience.
Source: All-College email
Construction Updates - September 19, 2019
Tomorrow—Friday, September 19—facilities will be performing preventive maintenance on ceiling units in B135A and B135B. Adjacent offices may experience some noise during this maintenance.
Source: All-College email
Construction Updates - August 19, 2019
C-Building heating and air conditioning maintenance work is scheduled to begin tomorrow, August 20, at 6:30 a.m. The project will continue for two weeks, causing disruptions to office spaces, hallways and C202. During the maintenance, C202 will be closed for two days. More information to follow regarding a timeline for access to individual offices and C202 closures.
Construction Updates - August 1, 2019
The following projects are scheduled for Friday, August 2:
- Sprint and Comcast will be working in the first-floor corridor of the D-Building to install fiber optic cables. Please use caution as you travel through this area.
- Carpet will be installed in room B124 (the music room). The room will be closed during the installation.
- Between 7-10 a.m., contractors are scheduled to repair the “grab-n-go” cooler inside Central Café in the B-Lobby. The contractor will be brazing the copper lines which will produce odor and a burnt smell throughout the B-Lobby; however, the B-Lobby will be safe for visitors during these repairs.
Source: All-College email
Construction Updates - July 30, 2019
On Friday, August 2, Sprint and Comcast will be working in the first-floor corridor of the D-building to install fiber optic cables. please use caution as you travel through this area.
Source: All-College email
Construction Updates - July 24, 2019
On Friday, July 26 from 6 a.m. – 2 p.m. the second floor, C-Building walkway (connecting B-building and D-Building), will be closed for roof drain repairs. During this time, students, faculty and staff can travel between B-Building and D-Building by using the first or third floor.
Source: All-College email
Construction Updates - July 19, 2019
The pothole repairs for Parking Lot 4 and 5 will be completed today. Due to hot temperatures, extra time is needed for the asphalt to settle. Parking Lot 4 will remain closed through Saturday, July 20 and will reopen the morning of Sunday, July 21. Parking Lot 5 will be closed throughout the weekend and will reopen on Monday, July 22.
Source: All-College email
Construction Updates - July 11, 2019
Repairs to potholes are scheduled for Parking Lots 4 and 5 and the Perimeter Road on Friday, July 19, 2019, beginning at 8 a.m. During this time, we will be closing off portions of Parking Lots 4 and 5 as well as the Perimeter Road parallel to New Rutherford Ave. to ensure the safety of students, faculty and staff. If the work is not completed on Friday, July 19, the project will continue on Saturday, July 20, 2019.
Please note: repairs that were previously scheduled for this Friday, July 12, have been canceled.
Please stay tuned for updates and check the facilities updates web page for the latest information. We apologize for any inconvenience as we continue to make improvements to our campus.
Source: All-College email
Construction Updates - July 8, 2019
Please be cautious as you enter/exit the building through the main lobby of the B-Building on July 9, 2019. In our effort to correct minor water leakage problems associated with the main entrance to B–Building at the plaza, a consultant will be on campus performing a water test in multiple locations. Please be alert as you enter and exit through the main lobby.
Source: All-College email
Construction Updates - June 28, 2019
Repairs are scheduled for Parking Lots 4 and 5 and the Perimeter Road on Friday, July 12, 2019. During this time, we will be closing off portions of Parking Lots 4 and 5, as well as the Perimeter Road parallel to New Rutherford Ave. to ensure the safety of students, faculty and staff.
If the work is not completed on Friday, July 12, the project will continue on Saturday, July 13, 2019.
Source: All-College email
Construction Updates - June 24, 2019
Repairs are scheduled for Parking Lots 4 and 5 and the Perimeter Road on Friday, June 28, 2019. During this time, we will be closing off portions of Parking Lots 4 and 5, as well as the Perimeter Road parallel to New Rutherford Ave. to ensure the safety of students, faculty and staff.
If the work is not completed on Friday, June 28, the project will continue on Saturday, June 29, 2019.
Please stay tuned for updates and check the facilities updates web page for the latest information.
We apologize for any inconvenience as we continue to make improvements to our campus.
This email may contain information that is privileged and confidential. If you suspect that you were not intended to receive it, please delete it and notify the sender as soon as possible.
Source: All-College email
Construction Updates - June 12, 2019
The sink located in the Faculty and Staff Lounge, C316, will be out of service from Thursday, June 13 through Tuesday, June 18, 2019. Facilities will be installing a new base cabinet, sink and disposal.
Please stay tuned for updates and check the facilities updates web page for the latest information.
We apologize for any inconvenience as we continue to make improvements to our campus.
Source: All-College email
Temporary H-Building Class Relocations for June 4, 2019
Due to a water main break, H-building will remain closed for June 4, 2019. For the remainder of the day, all H-Building classes are relocated to main campus - unless otherwise noted by your professor/instructor. See details below.
Course Section |
H-Building Location |
Moved To |
BIO-205-BE2 5-10 p.m. |
H176 |
B105 |
BSL-001-L6 6-9 p.m. |
H120 |
B104 |
BSL-002-L6 6-9 p.m. |
H155 |
B110 |
BSL-004-L5 6-9 p.m. |
H148 |
B126 |
EMC-003-A01 3-8 p.m. |
H167 |
B127 |
EMC-003-A02 3-8 p.m. |
H167 |
B127 |
EMC-003-A04 3-8 p.m. |
H167 |
B127 |
NON-102-NO1 6-9 p.m. |
H170 |
B132 |
Charlestown Campus Construction Updates - June 3, 2019
The following is an update on the ADA sidewalk construction project:
The construction of the ADA sidewalks is progressing rapidly.
The next phase for the project will begin on Tuesday June 4, 2019 in Parking Lot 5.
- Initial work will take place at the Rutherford Ave. end of Lot 5 - connecting the Rutherford Ave. sidewalk to the walking trail at the athletic field.
- The scope of work will also include connecting Lot 5 to the ADA ramp at the G-Building entrance on the opposite end of Lot 5.
Please be careful you as walk or drive in these areas.
The contractor will be closing portions of Lot 5 to ensure the safety of students, faculty and staff during construction.
Please stay tuned for updates and check the facilities updates web page for the latest information.
We apologize for any inconvenience as we continue to make improvements to our campus.
Source: All-College email
Construction Updates - May 28, 2019
Please note, there is an update to the perimeter road closure schedule. The perimeter road will be closed May 29-May 31. Please see the full updated perimeter road closure schedule below.
Exterior Walkway Improvements
Bunker Hill Community College has received funding from the Division of Capital Asset Management & Maintenance (DCAMM) to improve the exterior sidewalks and accessible ramps at strategic locations on campus in compliance with current ADA standards.
The construction of the ramps and walkways will require temporary closure of certain faculty and staff parking lots and roadways to ensure the safety of the BHCC community and the construction workers. Below is a summary of the closures:
The perimeter road will be closed May 29 – May 31, 2019.
- The Rutherford Avenue entrance will still be accessible, allowing access to faculty and staff Lots 5-6 and the perimeter road leading up to the Rutherford Avenue exit. To access student parking, guest parking, and faculty and staff Lots 3-4 during this time, vehicles should enter campus between Lots 1 and 2.
- Some areas of faculty and staff Lot 5 will be closed from May 11 – June 7, 2019.
These dates are target dates. As with all exterior construction, the activities are weather dependent. Please stay tuned for updates, and check the facilities updates web page for the latest information.
We apologize for any inconvenience as we continue to make improvements to our campus.
Source: All-College email
Construction Updates - April 11, 2019
Trio Student Success Program Relocation
As of Tuesday, April 16, 2019, the Trio Student Success Program will be relocated to room E226. This room is located inside Lifemap.
Exterior Walkway Improvements
BHCC has received funding from the Division of Capital Asset Management & Maintenance (DCAMM) to improve the exterior sidewalks and accessible ramps at strategic locations on the Charlestown Campus in compliance with current ADA standards. To allow for these improvements, portions of parking Lot 5 and the perimeter road will be closed periodically throughout the construction. The perimeter road will be closed beginning at the Rutherford Avenue exit from April 22 – May 13, 2019 and May 31 – June 4, 2019. Some areas of faculty and staff Lot 5 will be closed from May 11 – June 7, 2019. These dates are target dates. As with all exterior construction, the activities are weather dependent. Please stay tuned for updates and check the facilities updates web page for the latest information.
Construction Updates - May 9, 2019
Exterior Walkway Improvements
BHCC has received funding from the Division of Capital Asset Management & Maintenance (DCAMM) to improve the exterior sidewalks and accessible ramps at strategic locations on the Charlestown Campus in compliance with current ADA standards. To allow for these improvements, portions of parking Lot 5 and the perimeter road will be closed periodically throughout the construction. The perimeter road will be closed beginning at the Rutherford Avenue exit from April 22 – May 13, 2019 and May 31 – June 4, 2019. Some areas of faculty and staff Lot 5 will be closed from May 11 – June 7, 2019. These dates are target dates. As with all exterior construction, the activities are weather dependent.
Parking Lot Line Painting Rescheduled
The parking lot painting project, scheduled for April 14 and 15 has been rescheduled for May 13 and 14 from 10 p.m. – 6 a.m. The scope of work includes parking lots 3 through 6, the roadside parking spots and the crosswalks. No overnight parking will be permitted on May 13 and 14.
Please stay tuned for updates and check the facilities updates web page for the latest information.
Source: BHCC Updates
Construction Updates - May 16, 2019
Parking and Pedestrian Line Painting - Rescheduled
Due to rain, the exterior line painting has been rescheduled for pedestrian walkways as well as parking lots 3, 4, 5 and 6 and curbside parking spaces. The work will now be completed on Monday, May 20, and Tuesday, May 21, between the hours of 10 p.m. and 6 a.m.
No overnight parking is permitted on these dates.
Please note, there is an update to the perimeter road closure schedule. The perimeter road will be open for Commencement on May 23. Please see the full updated perimeter road closure schedule below.
Exterior Walkway Improvements
Bunker Hill Community College has received funding from the Division of Capital Asset Management & Maintenance (DCAMM) to improve the exterior sidewalks and accessible ramps at strategic locations on campus in compliance with current ADA standards.
The construction of the ramps and walkways will require temporary closure of certain faculty and staff parking lots and roadways to ensure the safety of the BHCC community and the construction workers. Below is a summary of the closures:
The perimeter road is currently closed through May 22, 2019. The perimeter road will reopen for Commencement on May 23 through May 30, 2019. The road will be closed again, May 31 – June 4, 2019.
- The Rutherford Avenue entrance will still be accessible, allowing access to faculty and staff Lots 5-6 and the perimeter road leading up to the Rutherford Avenue exit. To access student parking, guest parking, and faculty and staff Lots 3-4 during this time, vehicles should enter campus between Lots 1 and 2.
- Some areas of faculty and staff Lot 5 will be closed from May 11 – June 7, 2019.
These dates are target dates. As with all exterior construction, the activities are weather dependent. Please stay tuned for updates, and check the facilities updates web page for the latest information.
We apologize for any inconvenience as we continue to make improvements to our campus.
Source: BHCC Updates
Construction Updates - May 2, 2019
Exterior Walkway Improvements – Perimeter Road Closure
BHCC has received funding to improve the exterior sidewalks and accessible ramps at strategic locations on the Charlestown Campus in compliance with current ADA standards. To allow for these improvements, the perimeter road (running alongside B-Building) will be closed from April 22 – May 13, 2019 and May 31 – June 4, 2019. To access campus by car during these closures, please enter campus between lots 1 and 2. These dates are target dates. As with all exterior construction, the activities may be affected by weather. Please stay tuned for updates and check the facilities updates web page for the latest information.
Source: BHCC Updates
Construction Updates - April 4, 2019
Exterior Walkway Improvements
BHCC has received funding from the Division of Capital Asset Management & Maintenance (DCAMM) to improve the exterior sidewalks and accessible ramps at strategic locations on the Charlestown Campus in compliance with current ADA standards. To allow for these improvements, portions of parking Lot 5 and the perimeter road will be closed periodically throughout the construction. The perimeter road will be closed beginning at the Rutherford Avenue exit from April 22 – May 13, 2019 and May 31 – June 4, 2019. Some areas of faculty and staff Lot 5 will be closed from May 11 – June 7, 2019. These dates are target dates. As with all exterior construction, the activities are weather dependent. Please stay tuned for updates, and check the facilities updates web page for the latest information.
Source: BHCC Updates
Charlestown Campus Construction Updates - May 14, 2019
Please note, there is an update to the perimeter road closure schedule. The perimeter road will be open for Commencement on May 23. Please see the full updated perimeter road closure schedule below.
Exterior Walkway Improvements
Bunker Hill Community College has received funding from the Division of Capital Asset Management & Maintenance (DCAMM) to improve the exterior sidewalks and accessible ramps at strategic locations on campus in compliance with current ADA standards.
The construction of the ramps and walkways will require temporary closure of certain faculty and staff parking lots and roadways to ensure the safety of the BHCC community and the construction workers. Below is a summary of the closures:
The perimeter road is currently closed through May 22, 2019. The perimeter road will reopen for Commencement on May 23 through May 30, 2019. The road will be closed again, May 31 – June 4, 2019.
- The Rutherford Avenue entrance will still be accessible, allowing access to faculty and staff Lots 5-6 and the perimeter road leading up to the Rutherford Avenue exit. To access student parking, guest parking, and faculty and staff Lots 3-4 during this time, vehicles should enter campus between Lots 1 and 2.
- Some areas of faculty and staff Lot 5 will be closed from May 11 – June 7, 2019.
These dates are target dates. As with all exterior construction, the activities are weather dependent. Please stay tuned for updates.
We apologize for any inconvenience as we continue to make improvements to our campus.
Source: All College email
Temporary H-Building Class Relocations for April 20 and 21, 2019
The H-building is closed for the weekend of April 20 and 21 due to the water main break on April 19, 2019. Saturday and Sunday classes have been relocated to other locations. See details below.
BHCC courses that have been relocated:
Saturday, 4/20/2019
Course Section |
H-Building Location |
Moved To |
BLL-001-S1 8:15-11:55 a.m. |
H120 |
B135A |
BSL-001-S1 8:15-11:55 a.m. |
H152 |
B217 |
BSL-002-S1 8:00-11:40 a.m. |
H125 |
D216 |
BSL-002-S2 12:00 – 3:40 p.m. |
H125 |
B104 |
BSL-003-S1 8:00-11:40 a.m. |
H149 |
B110 |
BSL-003-S2 12:00 – 3:40 p.m. |
H149 |
B108 |
BSL-004-S1 12:00 – 3:40 p.m. |
H149 |
B105 |
EMC 004-S1 9:00 a.m. – 3:00 p.m. |
H174 |
B125 |
Sunday, 4/21/2019
Course Section |
H-Building Location |
Moved To |
BSL-003-SU 12:00 – 3:40 p.m. |
H149 |
B112 |
EMC 004-S1 9:00 a.m. – 3:00 p.m. |
H174 |
B125 |
Charlestown Campus Construction Updates - April 23, 2019
Exterior Walkway Improvements
Bunker Hill Community College has received funding from the Division of Capital Asset Management & Maintenance (DCAMM) to improve the exterior sidewalks and accessible ramps at strategic locations on campus in compliance with current ADA standards.
The construction of the ramps and walkways will require temporary closure of certain faculty and staff parking lots and roadways to ensure the safety of the BHCC community and the construction workers. Below is a summary of the closures:
- The perimeter road is currently closed beginning at the Rutherford Avenue exit until May 13, 2019, and will also be closed from May 31 – June 4, 2019. The Rutherford Avenue entrance will still be accessible, allowing access to faculty and staff Lots 5-6 and the perimeter road leading up to the Rutherford Avenue exit. To access student parking, guest parking, and faculty and staff Lots 3-4 during this time, vehicles should enter campus between Lots 1 and 2.
- Some areas of faculty and staff Lot 5 will be closed from May 11 – June 7, 2019.
These dates are target dates. As with all exterior construction, the activities are weather dependent. Please stay tuned for updates.
Source: All College email
Construction Updates - April 9, 2019
On April 9 and 10, there will be construction on a concrete pad for a new cardboard compactor at the loading dock of E-building. There will be slight disruption in traffic flow and noise pollution during this operation.
On April 11 and 12, ceiling tiles will be replaced in the mailroom. There will be no disruption to mail services.
Mark-A-Lot will be painting lines on the roadways and parking lots on April 14 and 15. We will do our best to minimize the disruption of traffic flow in the area.
We apologize for any inconvenience as we continue to make improvements to our campus. Please stay tuned for regular construction updates—via email, on our new facilities updates web page and in the BHCCUpdates—as our progress continues.
This email may contain information that is privileged and confidential. If you suspect that you were not intended to receive it, please delete it and notify the sender as soon as possible.
Source: All College email
Coil Cleaning on Charlestown Campus – March 6, 2019
Regular heating coil maintenance has been scheduled for the B- and C-Buildings on Wednesday, March 6, between the hours of 6-8 a.m. The work area (between the B-Lobby and C-Building) will be closed off during this time.
We apologize for any inconvenience as we continue to make improvements to our campus. Please stay tuned for regular construction updates—via email, on our new facilities updates web page and in the BHCCUpdates—as our progress continues.
Source: All College email
Construction Updates - February 7, 2019
B-Lobby and Student Central is now open. B-lobby renovations have been finalized. We hope you’re enjoying the recent updates to the B-Lobby and Student Central.
Please stay tuned for regular construction updates—via email, on our new facilities updates web page and in the BHCCUpdates—as our progress continues.
Source: BHCC Updates
Construction Updates - January 31, 2019
B-Lobby and Student Central is now open. B-lobby renovations have been finalized. We hope you’re enjoying the recent updates to the B-Lobby and Student Central.
Please stay tuned for regular construction updates—via email, on our new facilities updates web pageand in the BHCCUpdates—as our progress continues.
Source: BHCC Updates
Construction Updates - January 24, 2019
B-Lobby and Student Central now open. B-lobby renovations were finalized last week. We hope you’re enjoying the recent updates to the B-Lobby and Student Central.
Please stay tuned for regular construction updates—via email, on our new facilities updates web page and in the BHCCUpdates—as our progress continues.
Source:BHCC Updates
Construction Updates - January 17, 2019
Please be cautious and follow the temporary aisle ways that have been created for your safety. We are on target to complete the construction January 15, 2019, with a few items to finish the following week.
We apologize for any inconvenience as we continue to make improvements to our campus. Please stay tuned for regular construction updates—via email, on our new facilities updates web page and in the BHCCUpdates—as our progress continues.
Source:BHCC Updates
Construction Updates - December 9, 2018
B-Building Student Central Lobby Hallway Temporary Changes
On Monday, December 3, 2018, a temporary hallway will be built in the B-Building Lobby. This hallway will be on the left side of the lobby, near Central Café, to allow for installation of the floor tile, ceiling, walls and lighting while the College is closed from December 22, 2018 - January 1, 2019. For your safety, please be aware of your surroundings as the B-Building construction lobby project enters its final stages.
Source:BHCC Updates
Construction Updates - November 18 and November 25, 2018
Parking Lot 6 on the Charlestown Campus
The line stripping of the new parking spaces in Lot 6 is completed.
Source:BHCC Updates
Construction Updates - November 11, 2018
MathSpace Relocation
As of Monday, November 5, 2018, the MathSpace has been relocated to room E234.
B-Building Fire Alarm Update
Last Thursday and this past Saturday, the fire alarm in the B-Building was activated due to faulty smoke detectors that may have been the result of excess construction dust. When there is an alarm, Boston Fire responds immediately to determine if there is a threat which they did in all cases.
H-Building: Water Update
The sediment in the tap water in the H-Building has been resolved. H-Building management has switched the water supply to a new main. There should be improved results over the next few days. Please continue to utilize the water coolers located in the student lounge and staff lounge for drinking.
Parking Lots 5 & 6 on the Charlestown Campus
There was removal of an underground storage tank which is now complete. BHCC requested the contractor to remove the grass island and partial sidewalk to create additional parking spaces which has been paved. The line stripping of the new parking spaces will be complete by November 16, 2018.
Source:BHCC Updates
Construction Updates - November 4, 2018
MathSpace Relocation
Following the closure of the M-Building on the main campus, MathSpace has been relocated to room E234. The new location will re-open on Monday, November 5, 2018
H-Building: Water Update
It has come to our attention that there is some sediment in the tap water in the H-Building. This is likely caused by the construction work at Hood Business Park. Facilities is working with Hood management to determine the cause and a solution. In the meantime, please continue to utilize the water coolers located in the student lounge and staff lounge for drinking. There is also a filtered water station located outside of the conference room, room H130.
B-Building Elevators – November 9-13, 2018
The B-Building elevator will be out of service beginning at 9 p.m. on Friday, November 9 and will return to service at 6 a.m. on Tuesday, November 13. Please use the elevators in C-Building or D-Building during this time.
B-Building Second Floor Corridor – November 21-25, 2018
The contractors will perform demolition and floor prep during the Thanksgiving break beginning Wednesday evening, November 21, through Sunday, November 25. The B-Building second floor lobby hallway access to C-Building will be closed during this time. The area will re-open Monday morning, November 26. As a reminder, the College will be closed November 22-25 for Thanksgiving Recess.
Administrative Offices – B-Building, Third Floor – December 26, 2018-January 2, 2019
The ceilings in the administrative offices in the B-Building will be replaced beginning December 26, 2018, and will be completed on or before January 2, 2019.
Source:BHCC Updates
Temporary H-Building Class Relocations for February 2, 2019
Due to an emergency maintenance request from Eversource, the H-Building will be closed Saturday morning, 2/2/19. Classes are NOT canceled, morning classes at H-building have been relocated to the main campus. Classes starting at 12 p.m. or later will be held in their regularly scheduled locations. Please see facilities updates page on website for list of the relocations.
BHCC courses that have been relocated:
Course Section | H-Building Location | Moved To |
---|---|---|
BSL-003-S1 8:15-11:55 a.m. | H149 | B109 |
BSL-001-S1 8:15-11:55 a.m. | H152 | B112 |
BLL-001-S1 8:15-11:55 a.m. | H120 | B113 |
BSL-003-S2 8:15-11:55 a.m. | H149 | B114 |
BSL-002-S2 8:15-11:55 a.m. | H125 | B110 |
Lesley University events that have been relocated:
Course Section | H-Building Location | Moved To |
---|---|---|
CPSYC 2421 BH01 Intro to Counseling 9 a.m-1 p.m. | H176 | G138 |
CLITR 3315 Contmp. Latin A Wom Writing 9 a.m-1 p.m. | H167 | G227 |
Business Analytics 9 a.m-1 p.m. | H175 | G139 |
The following H-Building classes on Saturday, February 2 have not been relocated, they will meet as scheduled in their regular rooms:
BLL-001-S2 12-3:40 p.m.
BSL-002-S1 12-3:40 p.m.
BSL-003-S3 12-3:40 p.m.
BSL-004-S1 12-3:40 p.m.
Construction Updates - January 3, 2019
Water Temporarily Shut off in B-Building
Water will be temporarily shut off on Friday, January 4, 2019 from 6 -9 a.m. in the B-building. During this time, restrooms in the-B Building will be closed. Restrooms in Buildings C, D, E and G will be open.
Fire Alarm Installation
The B-building lobby construction is in its final stage. Overhead work being completed this week includes ceilings, lighting, exit signage and fire alarm testing.
Testing of the new fire alarm installation will take place on Thursday (1/3/19) and Friday (1/4/19). Each device on the second floor of the B-building will be tested and will include sounds from horns and flashing strobe lights.
This is only a test. In the event of an emergency you will be notified to evacuate the building.
Please be cautious and follow the temporary aisle ways that have been created for your safety. We are on target to complete the construction January 15, 2019, with a few items to finish the following week.
We apologize for any inconvenience as we continue to make improvements to our campus. Please stay tuned for regular construction updates—via email, on our new facilities updates web page and in the BHCCUpdates—as our progress continues.
Source: BHCC Updates
Construction Update - No water from 6 - 9 a.m. on Friday, January 4, 2019 in B-building
Water Temporarily Shut off in B-Building
Water will be temporarily shut off on Friday, January 4, 2019 from 6 -9 a.m. in the B-Building. During this time, restrooms in the-B Building will be closed. Restrooms in Buildings C, D, E and G will be open.
We apologize for any inconvenience as we continue to make improvements to our campus. Please stay tuned for regular construction updates—via email, on our new facilities updates web page and in the BHCCUpdates—as our progress continues.
Source: All College email
Construction Update - January 2, 2019
The B-building lobby construction is in its final stage. Overhead work being completed this week includes ceilings, lighting, exit signage and fire alarm testing.
Testing of the new fire alarm installation will take place on Thursday (1/3/19) and Friday (1/4/19). Each device on the second floor of the B-building will be tested and will include sounds from horns and flashing strobe lights.
This is only a test. In the event of an emergency you will be notified to evacuate the building.
Please be cautious and follow the temporary aisle ways that have been created for your safety. We are on target to complete the construction January 15, 2019, with a few items to finish the following week.
Source: All College email
Construction Update: Reminder, BHCC Closed December 22, 2018 at 3:30 p.m. - January 1, 2019
A reminder that the College will be closed December 22, 2018 at 3:30 p.m. – January 1, 2019
During this time, installation of the floor tile, ceiling, walls and lighting will take place in the Student Central area of the B-lobby. There may also be times when the water is shut off.
We apologize for any inconvenience as we continue to make improvements to our campus. Please stay tuned for regular construction updates—via email, on the facilities updates web page and in the BHCCUpdates—as our progress continues.
Source: All College email
Construction Updates - December 11, 2018
Upcoming Construction on the Main Plaza
On Wednesday, December 12, 2018, the general contractor will be coring holes in the plaza concrete slab in front of the exterior door leading to the construction area from the main entry plaza. There will be no change in access to B – building lobby. Please exercise caution as you enter and exit the main entrance.
Source: All-College email
Construction Updates - November 30, 2018
B-Building Student Central Lobby Hallway Temporary Changes
On Monday, December 3, 2018, a temporary hallway will be built in the B-Building Lobby. This hallway will be on the left side of the lobby, near Central Café, to allow for installation of the floor tile, ceiling, walls and lighting while the College is closed from December 22, 2018 - January 1, 2019. For your safety, please be aware of your surroundings as the B-Building construction lobby project enters its final stages.
We apologize for any inconvenience as we continue to make improvements to our campus. Please stay tuned for regular construction updates here, via email, and in the BHCCUpdates—as our progress continues.
Construction Updates - September 21, 2018
Charlestown Campus Construction Update
Beginning September 21 and over the next week, the Student Central and Admissions Offices will move into their new locations in our newly renovated B-Lobby (second floor of the B-Building, just inside the main entrance off the plaza). Student Central staff will be manning the Welcome Desk to help answer your questions. Our next phase of construction will focus on completing the renovations on the second floor of the B-Building, in the area of the former Financial Aid and Student Payment windows. As part of this work, the Veterans Center has now been relocated to room E234. We appreciate your patience as we continue to make improvements to our campus.
Source: BHCC Updates
Construction Updates - November 6, 2018
MathSpace Relocation
As of Monday, November 5, 2018, the MathSpace has been relocated to room E234.
B-Building Fire Alarm Update
Last Thursday and this past Saturday, the fire alarm in the B-Building was activated due to faulty smoke detectors that may have been the result of excess construction dust. When there is an alarm, Boston Fire responds immediately to determine if there is a threat which they did in all cases.
H-Building: Water Update
The sediment in the tap water in the H-Building is being addressed. Facilities is working with Hood management to determine the cause and a solution. Hood management believes they have isolated the pipe that may have been causing the issue. There should be improved results over the next few days. In the meantime, please continue to utilize the water coolers located in the student lounge and staff lounge for drinking.
Parking Lots 5 & 6 on the Charlestown Campus
There was removal of an underground storage tank which is now complete. BHCC requested the contractor to remove the grass island and partial sidewalk to create additional parking spaces which has been paved. The line stripping of the new parking spaces will be complete by November 16, 2018.
We apologize for any inconvenience as we continue to make improvements to our campus. Please stay tuned for regular construction updates on this page, in email, and in the BHCC Updates as our progress continues.
Source: All-College email
Construction Updates - October 4, 2018
B-Building Plaza Entrance: Week of October 15, 2018
The architect and engineering consultant of record and the general contractor will be performing leak testing at the B-Building plaza entrance during the week of October 15. Two entry doors will be closed off during the investigation. Please observe the caution tape, orange cones and construction personnel, and exercise caution as you enter and exit the building.
B-Lobby Renovation Continues
The moves last week of Student Central, Admissions and Student Financial Services (B325) were successful. The contractor has taken full advantage and has completed the demolition of the Bursars and Financial Aid offices. The Veterans Center and B206A conference room have been removed and the floor is being prepared for tile. The target date for completion is January 15, 2019.
Faculty/Staff Parking Lot 6
The paving of lot 6 is on hold until dry weather returns.
Source: BHCC Updates
Construction Updates - October 11, 2018
B-Building Plaza Entrance
The architect and engineering consultant of record and the general contractor will be performing leak testing at the B-Building plaza entrance next week. Two entry doors will be closed off during the investigation. Please observe the caution tape, orange cones and construction personnel, and exercise caution as you enter and exit the building.
B-Lobby Renovation Continues
The moves last week of Student Central, Admissions and Student Financial Services (B325) were successful. The contractor has taken full advantage and has completed the demolition of the Bursars and Financial Aid offices. The Veterans Center and B206A conference room have been removed and the floor is being prepared for tile. The target date for completion is January 15, 2019.
Faculty/Staff Parking
The paving of lot 6 (adjacent to the loading dock) is on hold until dry weather returns.
Lot 3 (underneath the footbridge to the MBTA) will be closed for the next two weeks due to construction by NEL Corporation to the support structure of the Gilmore Bridge. The work should not affect the walking area between Lot 2 and the plaza. This work is scheduled to be completed by October 19.
Source: BHCC Updates
Construction Updates - October 18, 2018
B-Building Plaza Entrance
Leak testing at the B-Building plaza entrance continues, with two entry doors closed off during the investigation. Please observe the caution tape, orange cones and construction personnel, and exercise caution as you enter and exit the building.
B-Lobby Renovation Continues
New furniture has been installed as well as self-service kiosks for the Student Central area.
The Veterans Center and B206A Conference Room have been removed and the floor is being prepared for tile. The target date for completion is January 15, 2019.
Source: BHCC Updates
Construction Updates – November 1, 2018
MathSpace Relocation
Following the closure of the M-Building on the main campus, MathSpace has been relocated to room E234. The new location will re-open on Monday, November 5, 2018
H-Building: Water Update
It has come to our attention that there is some sediment in the tap water in the H-Building. This is likely caused by the construction work at Hood Business Park. Facilities is working with Hood management to determine the cause and a solution. In the meantime, please continue to utilize the water coolers located in the student lounge and staff lounge for drinking. There is also a filtered water station located outside of the conference room, room H130.
B-Building Elevators – November 9-13, 2018
The B-Building elevator will be out of service beginning at 9 p.m. on Friday, November 9 and will return to service at 6 a.m. on Tuesday, November 13. Please use the elevators in C-Building or D-Building during this time.
B-Building Second Floor Corridor – November 21-25, 2018
The contractors will perform demolition and floor prep during the Thanksgiving break beginning Wednesday evening, November 21, through Sunday, November 25. The B-Building second floor lobby hallway access to C-Building will be closed during this time. The area will re-open Monday morning, November 26. As a reminder, the College will be closed November 22-25 for Thanksgiving Recess.
Administrative Offices – B-Building, Third Floor – December 26, 2018-January 2, 2019
The ceilings in the administrative offices in the B-Building will be replaced beginning December 26, 2018, and will be completed on or before January 2, 2019.
Source: BHCC Updates
Charlestown Campus Construction Updates - October 25, 2018
MathSpace Relocation
Following the closure of the M-Building on the main campus, MathSpace has been relocated to room E234. The new location will re-open on Monday, November 5, 2018
B-Building Elevators – November 9-13, 2018
The B-Building elevator will be out of service beginning at 9 p.m. on Friday, November 9 and will return to service at 6 a.m. on Tuesday, November 13. Please use the elevators in C-Building or D-Building during this time.
B-Building Second Floor Corridor – November 21-25, 2018
The contractors will perform demolition and floor prep during the Thanksgiving break beginning Wednesday evening, November 21, through Sunday, November 25. The B-Building second floor lobby hallway access to C-Building will be closed during this time. The area will re-open Monday morning, November 26. As a reminder, the College will be closed November 22-25 for Thanksgiving Recess.
Administrative Offices – B-Building, Third Floor – December 26, 2018-January 2, 2019
The ceilings in the administrative offices in the B-Building will be replaced beginning December 26, 2018, and will be completed on or before January 2, 2019.
Source: All-College email
Charlestown Campus Construction Updates - October 22, 2018
M-Building Closed
M-Building on the main campus has been permanently closed and any classes have been relocated. Please visit our Facilities Updates web page at bhcc.edu/facilitiesupdates for a list of classroom and faculty office relocations. For additional information or questions, please contact the Office of the Dean of Science, Engineering, and Math at 617-228-3340.
H-Building Shuttle Stop
Following parking lot updates at the Hood Office Park, the H-Building Shuttle Stop has now been moved back to its original location at the front of the H-Building. The H-Building shuttle operates between the G-Building and the H-Building, running continuously Monday through Friday, 7:30 a.m.-10:05 p.m. and Saturday-Sunday 7:45 a.m.-4:05 p.m. Find more details at bhcc.edu/shuttleschedule.
We apologize for any inconvenience as we continue to make improvements to our campus. Please stay tuned for regular construction updates—via email, on our new facilities updates web page and in the BHCCUpdates—as our progress continues.
Source: All-College email
Fire Alarm Testing Buildings A - E
Per order of the Boston Fire Department, quarterly testing of the BHCC Fire Alarm system will take place October 23, 2018. You may hear intermittent alarms, horns and see flashing strobes. Please remember this is only a test.
In the event of an actual emergency during this time, you will receive instructions from Campus Police and/or Boston Fire Department.
Source: All-College email
Construction Updates - January 10, 2019
Please be cautious and follow the temporary aisle ways that have been created for your safety. We are on target to complete the construction January 15, 2019, with a few items to finish the following week.
We apologize for any inconvenience as we continue to make improvements to our campus. Please stay tuned for regular construction updates—via email, on our new facilities updates web page and in the BHCCUpdates—as our progress continues.
Source:BHCC Updates
Facilities Update: Fire Alarm Testing December 19-20
Fire Alarm Testing
On Monday, December 19 and Tuesday, December 20, fire alarm testing is scheduled for all buildings on the Charlestown Campus. The testing will be completed by end-of-day December 20. During testing, you may hear intermittent alarms and horns and see flashing strobes. Please remember this is only a test. In an actual emergency, you will receive instructions from Campus Police and/or the Boston Fire Department.
Source: All-College Email
Facilities Updates: December 8, 2022
Fire Alarm Testing
On Tuesday, December 13, fire alarm testing is scheduled for D Building on the Charlestown Campus. Testing will occur around 6 a.m. and should be completed by 9 a.m. During testing, you may hear intermittent alarms, horns, and see flashing strobes. Please remember this is only a test. In an actual emergency, you will receive instructions from Campus Police and/or the Boston Fire Department.
Source: All-College Email
Facilities Updates: October 17, 2022
C-Building Maintenance – hallway closure
Beginning October 24, 2022, the first floor C-Building hallway connecting B-Building and D-Building will be closed to remove, prepare, and replace the floor tile. To access the first floor of building B or D, please use the second floor and then the stairs to the first floor of B or D building. The closure will run through November 18, 2022.
Fire Alarm Testing
From Monday, October 24 through Wednesday, October 26, fire alarm testing is scheduled for buildings C and D on the Charlestown Campus. The testing will be completed by end-of-day Wednesday, October 26. During testing, you may hear intermittent alarms, horns, and see flashing strobes. Please remember this is only a test. In an actual emergency, you will receive instructions from Campus Police and/or the Boston Fire Department.
Source: All-College Email
Facilities Update September 17, 2022: BHCC Road Closure
Good morning,
Sorry for the late notification – On Monday, due to construction, if you are parking in lot 5, you may enter the BHCC Campus from Rutherford Ave. If you are parking elsewhere on the campus, please continue on Rutherford Ave cross Austin Ave and enter the BHCC campus between parking lots 1 & 2. Apologies for the inconvenience.
Thank you,
John Chirichiello
Bunker Hill Community College
Director of Facilities Management
Facilities Update: August 23, 2022
Sent on behalf of Gary Bigelow, Executive Director Facilities Planning, Construction & Energy Management
Notice to all who are driving to BHCC campus:
Eversource will periodically be closing the perimeter road on Wednesday, August 24 and possibly Thursday, August 25 to replace transformers on the MBTA property under and adjacent to the Gilmore Bridge and Parking Lot 3.
Facilities Update: July 21, 2022
Sent on behalf of Gary Bigelow, Executive Director Facilities Planning, Construction & Energy Management
The pedestrian bridge connecting the BHCC pedestrian plaza to Bunker Hill Mall will be closed July 25, 2022 through July 28, 2022 for repairs. Please plan your route accordingly.
Fire Alarm Testing - May 31, 2022
Sent on behalf of John Chirichiello, Director of Facilities Management
Dear BHCC Community,
On Wednesday, June 1 to Friday, June 3, fire alarm testing is scheduled for all buildings on the Charlestown Campus. The testing will be completed on Friday, June 3 by the end of the day. During testing, you may hear intermittent alarms, horns, and see flashing strobes. Please remember this is only a test. In an actual emergency, you will receive instructions from Campus Police and/or the Boston Fire Department.
FACILITIES UPDATE: Water service has been restored in A, B, and C Buildings - April 15, 2022
Sent on behalf of Gary Bigelow, Executive Director Facilities Planning, Construction & Energy Management
Dear BHCC Community,
Please be advised that water service has been restored to buildings A, B, and C.
Thank you for your patience during this campus renewal project.
Source: All-College Email
REMINDER - FACILITIES UPDATE: Water shut-off on Charlestown Campus in A, B and D buildings - April 14-15
Dear BHCC Faculty and Staff,
As a reminder, beginning tomorrow at noon, water in buildings A, B, and D will be shut off, and restrooms in those buildings will be closed until Friday afternoon. The Café in Student Central will also be closed from noon Thursday through Friday. Water in E and G Buildings will be on and restrooms in E and G will remain open.
Recognizing that the reduced number of restrooms may pose challenges, we encourage employees who are able to work remotely tomorrow and Friday to do so.
Tomorrow’s Spring Professional Development Day will be held online and employees can participate remotely. Those events begin at 1 p.m. (please see the earlier email today from BHCC Events for further Professional Development Day details).
Thank you for your patience as this important campus renewal work continues.
Source: All-College Email
Water shut-off on Charlestown Campus - April 12, 2022
On Thursday April 14, 2022 at noon, the water will be shut down in buildings A, B and D. Water will remain on in buildings E and G.
The restrooms will be closed and locked in the B-Building. The D-Building restrooms are blocked for the restroom renovation project and are not available. All restrooms will remain open in E and G.
The water will be restored late Friday afternoon on April 15, 2022.
Thank you for your cooperation.
Source: All-College Email
Facilities Update - April 11, 2022
Parking for the remainder of this week:
Beginning tomorrow, April 12, 2022, and for the next several days, the perimeter road ingress and egress from Rutherford Ave (southbound) will be closed.
Please enter the campus by traveling through the intersection at Rutherford Avenue and Austin Street and entering the campus between parking lots 1 and 2.
A barricade on the perimeter road at G-Building will direct all traffic into the gravel lot. Please exit the gravel lot in the direction of lots 1 and 2 to access Rutherford Avenue.
Thank you for your cooperation.
Source: All-College Email
D-Building Restrooms closed as part of the Restroom Renovation Project on the Charlestown Campus - April 5, 2022
Dear BHCC Community,
As part of the campus-wide Restroom Renovation project, we wanted to make the community aware of some upcoming changes to restroom availability on the Charlestown Campus.
As you may know, the College has embarked on a multi-phase project to upgrade restrooms and to create additional ADA compliant, gender-inclusive restrooms throughout our campus. The College is committed to providing safe and accessible campus restroom facilities to all members of our community. We encourage individuals to make choices about restroom usage based on their own level of comfort and their gender identity or expression. Our goal is to provide restroom facilities that meet a full spectrum of needs.
Beginning on Wednesday, April 6, 2022, all D-Building restrooms will be closed for renovation. We expect the renovations to be complete and to reopen the restrooms by early September. We are working on all of the D-Building restrooms simultaneously because the facilities are stacked vertically on floors 1, 2, and 3. While these facilities are closed, signage will be placed to direct users to available restroom. The closest restrooms to the D-Building are located in the E-Building.
The following restrooms are currently available:
E-Building – both men’s and women's restrooms on floors 1,2,3 & 4
G-Building - single-occupant/gender-inclusive restrooms on floors 1 & 2; both men’s and women's restrooms on floors 1
B-Building – one temporary, gender-inclusive multi-stall restroom on floor 1; men’s restrooms on floors 1,2, & 3; women’s restrooms on floors 2 & 3
Beginning on Wednesday, materials will be delivered to campus and temporary walls put in place to separate the work area from the hallway. As with many projects, there may be noise and dust generated during the demolition process, which our teams will work to mitigate as much as possible. Please understand this process is difficult and at times will be disruptive.
The restroom renovation project signifies another major step forward to achieving renewal of the BHCC physical plant. In the coming weeks, you will receive an update on plans for the Restroom Renovation project as well as construction of the new Academic Student Success Center.
Thank you for your cooperation and patience as we work to make this a better, more inclusive learning environment for the BHCC community.
Pam Eddinger, President
James Canniff, Provost/Vice President, Academic and Student Affairs
John Pitcher, Vice President, Administration and Finance
Gary Bigelow, Executive Director Facilities Planning, Construction & Energy Management
Source: All-College Email
Facilities Update -March 2, 2022
Parking Lot 4 Construction
The delivery of the jobsite office trailers has been delayed because of last week’s weather and the MDOT permits for oversize loads. The jobsite office trailers will be delivered on Monday, March 7 to parking lot 4. The electrician will begin preparations in the B1 electric closet on Thursday, March 3. Please be cautious if you are walking, riding, or driving on the perimeter road or connecting sidewalks on Monday, March 7.
Source: All-College Email
Facilities Update - February 7, 2022
Elevator Service Scheduled February 8-9, 2022
The elevator in the D-Building and the E1 elevator car in the E-Building will be taken out of service on Tuesday, February 8 and Wednesday, February 9 to update the software.
Please contact Facilities with questions or comments.
Source: All-College Email
Facilities Update - January 20, 2022
Elevator Test Thursday January 27 at 9 a.m.
The final test for Elevator E2 is scheduled for Thursday January 27 at 9 a.m. During the test, the fire alarm may sound at various intervals as each floor stop is being tested. Please disregard the alarm. If there is an emergency, BHCC Public Safety will provide direction. This is the final step in the Elevator Replacement project.